In Fort Mohave, Arizona, even Republican voters are fighting gas power plants as utilities try to lock in fossil fuels
…
Over the next few months, the Sunrise Hills retirees – among them many climate crisis skeptics and committed fossil fuel proponents – uncovered a trail of misinformation that appear to suggest MEC and Aepco, which is developing and will own and operate the gas combustion turbines, were at times opaque as they sought to fast track approval and circumvent closer scrutiny. MEC/Aepco “categorically deny” any effort to intentionally mislead anyone.
The retirees organized and began fact-checking and calling out claims about affordability, outages and low pollution made by MEC and Aepco in the glossy brochure and during public meetings.
It turned out that with a capacity of 98 megawatts, the two-turbine proposal fell just under the 100 MW limit that requires a state mandated comprehensive environmental review of impacts such as emissions, noise and water consumption by an expert committee at the state utility regulator, the Arizona corporation commission (ACC). Yet the utility has openly discussed plans to eventually double the size of the plant.
It also turned out that many of the county residents who spoke favorably of the plant in front of the board were in fact MEC employees and board members.
Removed by mod